11-10-2014, 05:18 PM
work has slowed down on the shop. good news is i will be done with my inside electrical and low voltage wiring in the next day or two. ends up the color of tile roof i have they didnt have enough in stock to do the shop so they are making it. so that slowed things donw by 2 weeks. it should be here this week we hope.
wednesday they will be out and trench for my main electrical line and hopefully run the conduit and wire and set the exterior meter panel.
things should start to speed up again this week.
tom
wednesday they will be out and trench for my main electrical line and hopefully run the conduit and wire and set the exterior meter panel.
things should start to speed up again this week.
tom